Does your building have a sidewalk shed in place?

Recent changes to NYC’s requirements make it especially important to coordinate permit renewals with a clear plan for the repairs that will allow the shed to be safely removed.
Sidewalk shed permits now require renewal every 90 days and no longer automatically renew in DOB NOW. Additional rules effective August 13, 2026 strengthen reporting and oversight requirements.
More Documentation at Renewal
Renewal submissions must include a report from a registered design professional documenting the building conditions associated with the shed, repair progress since the last renewal, work currently underway, and the estimated time needed to complete the repairs. Owners should coordinate with their engineer and permit applicant to keep project information current.
DOB also requires a $90 progress-report filing fee at each applicable renewal.
Longer Installations May Bring Additional Costs
Separate penalties may apply for failing to make repair progress, missing required progress reports, or missing façade repair milestones. Under the adopted rule, the one-time milestone penalties are:
- $5,000 for missing the construction-document filing milestone.
- $10,000 for missing the permit-application milestone.
- $20,000 for missing the repair-completion milestone.
*These penalties are subject to applicable extension and relief provisions. Separate monthly penalties for a lack of repair progress may also apply.
Repair Milestones Begin With the Shed Permit
For applicable FISP/Local Law 11 façade-repair sheds with initial permits issued on or after January 12, 2026, owners must track three milestones from the initial shed permit issuance date:
- Within 5 months: Submit the associated façade repair filing and complete construction documents.
- Within 8 months: Submit the associated contractor permit application and diligently pursue permit issuance.
- Within 24 months: Complete the repairs and obtain the Letter of Completion for the associated repair filing.
Renewing the shed permit does not restart these milestone deadlines. Owners should confirm which requirements apply to their shed and coordinate design, bidding, contractor approvals, and project closeout early.
Extensions Require Advance Planning
Extensions are subject to DOB approval, supporting documentation, and filing fees. The first two milestones may be extended in increments of up to 180 days. DOB may grant a single longer extension for the 24-month milestone based on the documented repair scope and schedule.
Requests may be submitted no earlier than 60 calendar days before the first 5-month milestone deadline and no later than 20 calendar days before the applicable milestone deadline. A registered design professional must submit the request.
DOB filing fees for extension requests are:
- 5-month milestone: $410.
- 8-month milestone: $465.
- 24-month milestone: $1,425.
**These filing fees are separate from professional service fees and any applicable penalties.
Owners should not assume that funding delays qualify a project for a milestone extension. Discuss potential delays with the project engineer early; a shed permit renewal and a repair milestone extension are separate requirements.
Plan the Next Steps Now
Review your permit expiration date, outstanding repair scope, project schedule, and any access or funding issues that could delay the work. Addressing these items early can help keep the repair process moving toward safe shed removal.
Merritt Engineering can assist with façade evaluations, repair design, and construction monitoring to help owners move from identifying building conditions to completing the necessary restoration work.