A complete structural restoration of the tower’s parking garage was engineered by Merritt, including demolition and re-pouring of sections of concrete slabs, repairs and replacements of corroded reinforcing steel, repairs and re-surfacing of damaged concrete, replacement of drains, and the application of a waterproof, oil-resistant deck coating.
Partitioning of the project into four separate phases and close monitoring of the construction progress allowed the 24 hour garage to maintain its day-to-day operations with minimal service disruptions.